The basics
The City of Allen requires a fence permit for any new fence over 30 inches tall. This includes like-for-like replacement of an existing fence — Allen is one of the stricter cities for permit enforcement in our service area. Code inspectors actively patrol construction sites and have issued stop-work orders on un-permitted installs.
What it costs
Allen's residential fence permit fee is typically $45–$65. Pool barriers and corner lots may run higher due to additional review. Verify current rates on the City of Allen permits page.
Application requirements
- Site plan with property lines, easements, and proposed fence location
- Materials and height specification
- Gate locations and widths
- Contractor license verification
- HOA approval letter (most Allen subdivisions require one)
Timeline
Standard residential: 5 business days. Pool barriers: 7–10 days. Allen's permit office runs on a tight, predictable schedule — applications submitted Monday morning are usually issued Friday of the same week.
HOA approval in Allen subdivisions:
- Twin Creeks: 1–2 weeks. ARC meets weekly. Cedar required, dark-stain palette.
- Watters Creek: 2–3 weeks. ARC meets twice monthly.
- Star Creek: 1–2 weeks. Standard cedar or composite. Picket gates approved.
- Bethany Lakes: 2 weeks. Cedar board-on-board preferred.
Allen height and zoning rules
- Front yard: 4 ft maximum, picket or open-style only
- Back and side yard: 8 ft maximum
- Corner lots: Standard side-yard rules apply 15 ft from right-of-way
- Pool barriers: 48 inches minimum, self-closing self-latching gate, picket spacing under 4 inches
- Easements: Fence cannot block utility easement access; drawing must show
Inspection
Allen inspectors check at frame stage (posts in concrete, rails attached, pickets not yet installed). They verify:
- Post depth matches permit (we install 30 inches for 6-ft, 36 inches for 8-ft)
- Concrete in every post hole
- Posts plumb
- Setback from property lines and easements as drawn
- Gate framing and hardware (custom-built cedar gate, three hinges)
Allen inspectors are fast and consistent — we typically pass first time on a clean install.
What we handle
- Site plan drawing
- Permit application submission and fee payment
- HOA architectural review packet
- Inspection scheduling and on-site meeting
- Re-inspect if corrections needed
- Final permit close-out paperwork
Most of our Allen clients never speak to the city directly. They sign the estimate, we handle everything else.
Where this leads
See our fence installation service, the Allen service-area page, and cedar vs pine materials guide.
Sources
City of Allen — cityofallen.org. Verify current rates and code references with the Allen Building Inspection department before relying on this guide.